Virginia / 2023
2.1 billion gallons usedJLARC's estimate includes reclaimed water; it is not a tally of evaporative consumption. It cannot be treated as Virginia's directly comparable slice of the national consumption model. Audit, pp. 62–63 ↗
Construction peaks, tax receipts and local burdens belong on different lines.
AI-assisted writing, evidence-editor and publisher passes · Not independent human fact-checking
Last evidence review: . This is the review date, not the date every number was measured. A national model, a Virginia legislative audit, and local county and school records play different roles here.
Review update: November 9: No material change found in the national electricity, tax, water and jobs figures or published geographic numbers reviewed. All 52 tax-model rows and 56 QCEW records were rechecked. Electricity and taxes retain their 2024 model periods; national on-site water retains 2023. October 2026 sector payrolls remain 454,800, preliminary and seasonally adjusted, from the November 6 release. March 2026 QCEW geography remains separate. PJM warning versions and its dated winter outlook were reviewed; warnings are not outages or backup-diesel operation. DEQ’s November 6 report still ends daily fine-particle averages November 5 and records a November 4 sensor move. Its live values were not audited. Health-literature search cutoffs are unchanged.
November 5 outlook: adequate supply is a forecast, not a guarantee. PJM expects enough resources for expected winter conditions, while warning that reserve margins are tightening and exceptionally high generator outages could leave the system vulnerable. Its higher-stress analysis includes demand-response programs. PJM also says it has never had to use its authority to order large loads onto backup generation. That operator statement is not proof that every generator was idle or that nearby air was unaffected. Read the November 5 outlook and its limits.
November 5 update: Pennsylvania narrows the proposal. The PUC’s clarification stops seeking comments on PJM’s rejected IRAS mechanism while continuing its state emergency-curtailment proposal. The revised appendix keeps limited protection for separately identified essential real-time services when backup fails, fuel runs out or permit limits are reached—not a blanket data-center exemption. This is not a final shutoff rule or a record of outages or household savings. Read the November 5 clarification. Inspect the revised proposed appendix.
November 6 grid check: warnings are not outages. PJM's November 3 DOM transmission warning now records an end time of 00:56 on November 4. A separate DOM warning started at 06:22 on November 4 and now records an end at 21:06 on November 5. November 3 messages explicitly labeled DRILL describe a winter exercise, not actual emergency dispatch. These notices do not establish household outages, backup-diesel operation or a data-center contribution. November 3 warning and end time ↗ · November 4 transmission warning ↗ · Explicitly labeled winter drill ↗
October 14 follow-up: Oregon's governor requests a time-limited permit pause, not an operating-facility shutdown or measured harm. Read the October 9 letter's scope and tradeoff →
October 15 follow-up: PJM's October 14 version 4 list adds opacity to one resource's constraint column. A listed constraint is not a pollution reading or proof of operation. Inspect the dated revision →
October 16 review: PJM's October 15 account reports no use of large-load backup authority and adds preliminary maintenance-outage context. This is the operator's dated account, not proof every generator was idle or that neighbors faced no pollution. Read the updated operating account →
October 16 follow-up: PJM issued a capacity advisory for October 19, citing expected maintenance and construction outages. It warns of tightening capacity, not an inevitable household outage. Forecast demand and unavailable capacity are different measures. The advisory does not itself extend DOE's October 13–16 order. Read the new advisory and retained operating record →
October 19 review: a Pennsylvania proposal, not a shutoff rule. A notice published October 17 carries an October 1 tentative order seeking comments on data-center curtailment rules. Its appendix gives limited protection to separately identified digital services essential to critical facilities when backup fails, runs out of fuel or reaches permit limits. It is not a blanket "all data centers first" rule. The IRAS provisions depend on federal approval. FERC's October 9 order accepted a registry but rejected PJM's linked capacity and curtailment package. The inspected state docket lists a tentative order, not a final rule. Neither record proves an avoided outage or lower bills. Read the notice and appendix. Inspect the state docket. Read the earlier federal decision.
October 18 follow-up: a Pennsylvania cost-allocation dispute. Shapiro's October 15 petition seeks to join the PPL case. PPL's October 16 response cites existing safeguards and a proposed transmission rider. The inspected docket lists an active case. These competing positions are not a new rate ruling or measured household savings. Read both sides and the filing dates.
October 17 follow-up: DOE's inspected October 13–16 operating window has ended; reporting and compliance duties continue. The October 19 advisory is not a renewal. We also added a Stafford noise-baseline case: its April 30 report covers January–February measurements, not operating-facility noise or illness. Read the evidence and its limits →
October 16 correction: Our generator guide described the earlier guidance without the later final rule. Virginia published that rule October 5, with a November 4 effective date. Its text covers data centers applying for permits on or after July 1, 2026. These requirements are not a measurement of pollution reduction. Read the rule and its dates ↗
October 15 follow-up: Texas's attorney general announced water-reporting letters to data-center developments. The announcement is not a water-use measurement, a finding of harm or an adjudication of violations. The letters and responses were not inspected here. Read the office's announcement ↗
This is a U.S. fact file, not a Virginia-only verdict. A national industry-commissioned model estimates substantial state and local tax contributions; Loudoun separately reports actual property-tax revenue. Those are different records, not numbers to add together. Data centers also place demands on power, water and land. National totals cannot settle one utility’s rate case or a neighborhood’s water pressure. Start with the broad scale, then inspect the local tax terms, public costs and operating records. Neither a developer’s promise nor a national estimate settles the deal on your block.
Berkeley Lab estimates 66 billion liters—about 17.4 billion U.S. gallons—consumed on site by U.S. data centers in 2023. This December 2024 report is a model, not a nationwide meter census or an AI-only total. Consumption is water not returned to the immediate water cycle; withdrawals count water taken out, including water later returned. Water used to generate electricity is additional and excluded from this card. Original report, direct and indirect water, pp. 55–58 ↗
Why 2023? The newer 2025 Update revises electricity estimates; we have not verified a replacement national water-consumption total in it. The review date is not the measurement year. Nor have we verified a comparable, complete 50-state water breakdown. Missing states are unknown here, not zero. Read the newer report's scope ↗
JLARC's estimate includes reclaimed water; it is not a tally of evaporative consumption. It cannot be treated as Virginia's directly comparable slice of the national consumption model. Audit, pp. 62–63 ↗
ICPRB's estimated annual-average on-site consumption, not a current meter reading. The region spans state lines and overlaps Virginia; do not add these records. March 2026 regional analysis ↗
The six reviewed utilities differed substantially after reclaimed water was excluded. This local range is not a national share or a guarantee that a small statewide average means no local burden. Audit, p. 63 ↗
Ask locally for the same utility's metered deliveries, returned water, reclaimed supply and summer peak. The detailed regional discussion and risk guide below remain part of the ledger.
BLS estimates 454,800 U.S. payroll jobs in October 2026 in computing infrastructure providers, data processing, web hosting and related services. This seasonally adjusted survey estimate was released November 6 and is preliminary. September was revised from 453,800 to 454,800, so October is unchanged on the revised basis. It covers an industry, not just people working inside server buildings; construction and supplier jobs classified elsewhere are not an economic-impact multiplier to add here. BLS sector employment, October 2026 ↗
| Location | Payroll jobs |
|---|---|
| Alabama | 3,875 |
| Alaska | Withheld by BLS |
| Arizona | 10,748 |
| Arkansas | 3,772 |
| California | 84,174 |
| Colorado | 12,924 |
| Connecticut | 4,641 |
| Delaware | 447 |
| District of Columbia | 1,982 |
| Florida | 27,560 |
| Georgia | 26,003 |
| Hawaii | 514 |
| Idaho | 1,253 |
| Illinois | 16,887 |
| Indiana | 4,799 |
| Iowa | 3,670 |
| Kansas | 2,241 |
| Kentucky | 3,499 |
| Louisiana | 2,875 |
| Maine | 787 |
| Maryland | 5,487 |
| Massachusetts | 10,101 |
| Michigan | 9,738 |
| Minnesota | 7,381 |
| Mississippi | 1,025 |
| Missouri | 14,277 |
| Montana | 473 |
| Nebraska | 2,315 |
| Nevada | 3,244 |
| New Hampshire | 1,875 |
| New Jersey | 15,701 |
| New Mexico | 1,038 |
| New York | 30,042 |
| North Carolina | 12,109 |
| North Dakota | Withheld by BLS |
| Ohio | 13,630 |
| Oklahoma | 1,709 |
| Oregon | 7,681 |
| Pennsylvania | 13,670 |
| Rhode Island | 641 |
| South Carolina | 4,180 |
| South Dakota | Withheld by BLS |
| Tennessee | 7,533 |
| Texas | 47,535 |
| Utah | 7,656 |
| Vermont | 480 |
| Virginia | 24,831 |
| Washington | 21,552 |
| West Virginia | 1,248 |
| Wisconsin | 7,793 |
| Wyoming | 532 |
Original first-quarter 2026 industry CSV ↗ · Definitions, month fields and disclosure codes ↗
| County | Payroll jobs |
|---|---|
| Franklin County, Ohio | 4,744 |
| Dallas County, Texas | 6,800 |
| Loudoun County, Virginia | 1,800 |
| Maricopa County, Arizona | 9,271 |
Hosting and processing establishments can include off-site service roles, while workers at contractors may be classified in other industries. These are not verified staffing totals for physical data-center buildings. Inspect the source records ↗
A payroll job is not a promise of permanent local employment. BLS counts positions, not unique people or net jobs caused by a project. The Virginia audit's separately dated building example below—roughly 50 full-time operating workers versus a 1,500-worker construction peak—answers a different question. Ask for actual operating rosters, contractor scope and construction duration before comparing a specific project.
A 2026 working paper estimates that data-center growth lowered average U.S. residential electricity rates in 2015–2024 relative to the alternative without that growth. Its proposed mechanism is spreading fixed costs over more electricity sales. This is a statistical estimate, not a finding that every household's bill fell. Its causal interpretation depends on assumptions about where facilities locate. The authors warn that constrained supply or demand that never arrives could reverse the benefit. It adds a countercase, not a guarantee for today's buildout. Local charges and payment commitments still need checking. Watten, Bistline and Blanford: working paper, sections III–IV ↗
Oregon's July decision shows why cost allocation matters. Portland General Electric's approved package lowered average residential rates while raising data-center rates. These are July 8 changes against prior rates, not surveyed bills paid or a comparison with Virginia. The package also changed power costs and other charges, so it cannot isolate data centers' contribution to the decrease.
Changes against prior rates, not measured household spending. One utility and one effective-date change, not today's total tariff or a national result.
The September 15 compliance filing says it changes no existing rates. Its contract terms include minimum payments and exit-cost protection, with possible refunds when capacity is reused or exit charges exceed stranded costs. The docket records a September 10 judicial-review petition, not a court decision. Adopted terms do not prove future costs cannot shift. Ask locally which costs a large customer must cover if it leaves.
The first is a construction peak, usually during a 12–18-month build; the second is ongoing staffing. They are not layoffs or a forecast for every project.
The data-center total includes reclaimed water; JLARC does not give the comparison user's water-source mix here. This statewide scale cannot settle a local utility dispute: data centers accounted for 0.2%–21% of customer use at six reviewed utilities, excluding reclaimed water.
Virginia's Joint Legislative Audit and Review Commission (JLARC) reports that representatives described a typical 250,000-square-foot data center as having roughly 50 full-time operating workers, about half of them contractors. A single building can have around 1,500 workers on site at the peak of construction, which usually lasts about 12 to 18 months. Those are reported examples, not a headcount for every proposed project. A campus built in phases may sustain trade work longer; it should not relabel peak crews as permanent staff.
JLARC's statewide economic model estimated 74,000 jobs supported by the industry annually, including indirect and induced work. Most estimated benefits arose during construction. The audit also reported average annual pay of about $100,000 for data-center employees and contractors in Virginia, varying by role and region. That is a statewide figure, not a promised wage for every applicant. Read the state audit ↗
Across all 50 states and D.C., PwC estimates $84.2 billion in state and local tax contribution in 2024. Its May 2026 study was commissioned by the Data Center Coalition, the industry's trade association. The total includes direct activity, suppliers and household spending, including effects that cross state borders. Federal taxes are excluded from this figure. Original report, Table A-4, pp. 39–40 ↗
What this does—and does not—count. PwC uses IMPLAN economic modeling and government receipts data, which it says reflect incentives, credits and abatements. Its industry definition also covers computing, hosting and related infrastructure services, not physical server buildings alone. This is not an audited tally of checks from facility owners, new revenue caused solely by data centers, a 2026 forecast or a calculation of net public benefit after public costs. Definitions, pp. 7, 14–15; methods and limits, pp. 92–95 ↗
| Location | State + local |
|---|---|
| Alabama | $0.552 |
| Alaska | $0.088 |
| Arizona | $1.289 |
| Arkansas | $0.477 |
| California | $18.317 |
| Colorado | $1.920 |
| Connecticut | $0.847 |
| Delaware | $0.154 |
| District of Columbia | $0.331 |
| Florida | $4.219 |
| Georgia | $2.666 |
| Hawaii | $0.292 |
| Idaho | $0.283 |
| Illinois | $3.327 |
| Indiana | $0.790 |
| Iowa | $0.469 |
| Kansas | $0.443 |
| Kentucky | $0.567 |
| Louisiana | $0.528 |
| Maine | $0.237 |
| Maryland | $1.558 |
| Massachusetts | $2.384 |
| Michigan | $1.558 |
| Minnesota | $1.390 |
| Mississippi | $0.240 |
| Missouri | $1.349 |
| Montana | $0.145 |
| Nebraska | $0.348 |
| Nevada | $0.608 |
| New Hampshire | $0.284 |
| New Jersey | $3.456 |
| New Mexico | $0.346 |
| New York | $8.020 |
| North Carolina | $1.924 |
| North Dakota | $0.118 |
| Ohio | $1.692 |
| Oklahoma | $0.387 |
| Oregon | $1.429 |
| Pennsylvania | $2.593 |
| Rhode Island | $0.185 |
| South Carolina | $0.694 |
| South Dakota | $0.085 |
| Tennessee | $0.983 |
| Texas | $5.739 |
| Utah | $0.824 |
| Vermont | $0.147 |
| Virginia | $3.129 |
| Washington | $3.397 |
| West Virginia | $0.194 |
| Wisconsin | $1.133 |
| Wyoming | $0.073 |
The local portion includes local governments; do not add city or county examples to this total. These estimates are not a ranking of receipts from buildings in each state. Inspect the source's state/local columns ↗
Where are the actual collections? We have not verified a nationwide, data-center-specific receipts tally. The Census quarterly tax series reports collections by tax type, not a separate data-center payer category. State and local records can establish particular collections; Virginia's new consumption-tax receipt and Loudoun's property-tax example follow. Their different taxes and periods cannot be added to or directly compared with this broader 2024 model. Census coverage and classification ↗ Commissioner's study page ↗
November 1 addition / SCC account dated October 20. Virginia's Public Service Taxation Division reported receiving $26,007,117.46—about $26.0 million—in initial Data Center Electricity Consumption Tax remittances for July–August 2026 electricity use. Its September-remittance slide calculates about $100 million of tax on reported use; that is not money fully collected. The timeline says first remittances arrived September 23 and some arrived in early October. Billing and payment lags left more expected in October and November, not confirmed received here. Do not add this initial-cycle account to Finance's calendar-month receipt below; neither is an annual total. SCC presentation, pp. 3–5: timing, calculation and receipts ↗
Virginia / September 2026 / recorded collections. The state's September revenue table records $24.967 million—about $25.0 million—in Data Center Consumption Tax receipts. The October 16 finance letter calls September the first month of payments received and warns that billing timing and implementation factors leave collections short of the full liability for the first two months of electricity consumption. The table's $600 million fiscal 2027 estimate is a forecast, not money collected. This is one state's particular tax, not all taxes paid by data centers, a national receipt total or net public benefit. Do not add it to the 2024 model or Loudoun's different tax and period. September table, p. 1; amounts in thousands ↗ October 16 letter, p. 4: incomplete collections ↗
Other source limits: Review update: No material numerical change found in the four national figures and existing state/local records reviewed October 29. IEA's October policy review does not replace the U.S. water baseline. March 2026 water analysis retained. Regional figures remain 2025 estimates, not today's meter readings; FY2027 revenue is a forecast, not collected revenue. Grid costs: protective terms are not measured household savings. SCC lacks municipal responses; generator permits are not measured emissions. Virginia's guidance retains exceptions; a final rule published October 5 takes effect November 4. Added DEQ's October 23, 2026 ambient air record; it does not isolate generator emissions or establish illness. DOE's authority is not measured operation or harm. PJM's October 19 advisory, issued October 16, is not renewal. October 15's unused-backup account stays dated. Oregon's adopted-rate counterweight, not measured household savings. The working paper's 2015–2024 data is not a verified local bill decrease.
Loudoun County reports $1.2 billion in real-estate and equipment-property taxes from data centers for fiscal 2026, or 39% of its overall budget. The county says the revenue has helped it increase school funding, support public safety, libraries, parks and mental-health services, and pay for capital work such as schools, roads and bridges. Over time, the county says its residential real-property tax rate generally fell from $1.145 per $100 of assessed value in tax year 2016 to $0.805 in 2026, with data-center revenue helping make that possible. That is the rate, not everyone's bill: an individual homeowner can still pay more when assessed value rises. County revenue figures ↗ County budget and tax-rate explanation ↗
Loudoun's school division says its approved fiscal 2027 budget funds additional teachers and instructional support as well as salary and benefit investments. Together, these records support the conclusion that data-center tax revenue contributes to a school system with more resources. They do not trace a particular teacher's raise to a particular server building. The county collects into a broader budget, and elected officials decide what to fund. School division's approved-budget account ↗
JLARC documented substantial local revenue and real work. The same audit warned that rapid load growth could require difficult grid expansion and raise costs for other electricity customers. Water use varies by cooling system and site; some facilities use far more than a large office building. Noise and proximity to homes matter, too. Virginia's sales-tax exemption for qualifying data-center equipment is also a public cost to count beside revenue. None of this proves a facility near you is a bad deal. It means a local deal needs its own complete accounting. JLARC's benefits and costs ↗
A national estimate does not settle a neighborhood debate: Berkeley Lab models all U.S. data centers at 192 terawatt-hours in 2024, 4.7% of national electricity use. That is not an AI-only count or a meter reading for a proposed site. EIA's higher-demand scenario explores possible regional generation and wholesale-price effects; it is not an observed household bill. The decisive local documents are the utility tariff and rate case, interconnection and load records, water agreement, tax terms and actual operating reports. Berkeley Lab estimate ↗ EIA scenario ↗
An October 9 Senate staff report challenges how grid-expansion costs are divided; Google's original response describes infrastructure payments and binding commitments. Berkeley Lab's tariff review identifies protective mechanisms, not measured household savings. The local test is the approved cost allocation and who pays if demand falls short. Read the grid-cost record and its countercase →
October 13 follow-up: FERC accepted PJM's large-load definition and registry, effective October 12, but rejected the linked bring-new-capacity and mandatory-curtailment package. Tracking large customers is not the same as adding supply or guaranteeing lower bills. This October 9 tariff decision is separate from DOE's temporary emergency authority. Read the decision and its limits →
Virginia's auditors estimated that data centers used 2.1 billion gallons of water statewide in 2023, just over a third of it reclaimed rather than newly withdrawn. That was less than 0.5% of statewide withdrawals. The state's single largest industrial water user used about 36.5 billion gallons that year. That comparison punctures the idea that data centers are Virginia's dominant water user. It does not settle a local water dispute: at the six utilities the auditors reviewed, data centers accounted for 0.2% to 21% of customer water use after reclaimed water was excluded. Eleven individual buildings each used more than 50 million gallons. Place, source, season and cooling design change the answer. JLARC water findings, pp. 62–63 ↗
And yes, the rest of the water ledger deserves ink. EPA estimates U.S. residential outdoor use at nearly 8 billion gallons a day, mainly for landscaping, with as much as half lost to wind, evaporation or runoff from inefficient irrigation. That is a national estimate, not a measurement of Loudoun's lawns or leaky mains; we cannot subtract it from a Virginia data-center total. A street puddle is a storm-drainage problem, not automatically lost drinking water. To compare a proposed facility with local irrigation or pipe leakage, get the same utility's annual figures and put them in the same units. EPA irrigation facts ↗
The diesel comparison deserves the same discipline. If exhaust matters at a generator yard, it matters at a truck stop. JLARC found data-center backup generators made up less than 4% of Northern Virginia nitrogen-oxide emissions and 0.1% or less of its carbon-monoxide and particulate emissions. The auditors also warned that regional averages may miss concentrated exposure next to a facility, especially during a prolonged outage. We have no verified count of idling trucks at a comparable local stop, so we won't invent one. Compare the same pollutant, area and time period before declaring either source harmless or uniquely intolerable. JLARC air findings, pp. 58–60 ↗
Withdrawal is not the same as consumption: some water returns; some is lost, including through evaporation. ICPRB's March 2026 summary estimates Washington Metropolitan Area data centers at 1% of withdrawals but 9% of annual consumptive use for 2025, reaching up to 12% in summer. That is a different region and denominator from Virginia's audit, not a revised statewide figure. Its estimates combine utility records and modeling, with a 75% consumptive-use assumption. Reclaimed cooling supply can reduce drinking-water demand without eliminating evaporative losses. Small annual shares do not replace a drought-season water plan. Water summary, March 2026 ↗ Study methods, December 2025, pp. 6-12–6-20 ↗
Regional direct on-site estimates, not measurements of today's local conditions. Both links describe the same study.
Virginia's October 1, 2026 SCC return lists contracted demand in megawatts and generator permitting information. These figures are not annual electricity use or measured emissions. Municipal water responses were not received in time; the investigation remained ongoing. A missing return is not zero water use. The older audit and regional estimates above keep their own dates and scope. SCC return, pp. 1–2 →
Some impacts are recorded; some health concerns remain unproven at a particular facility. The question is what was measured, who was exposed, and what outcome the evidence establishes. These are reading tools, not diagnoses of neighbors or a medical assessment of a site. The overstatements below are examples to test, not quotations or a count of circulating posts.
Newer 2026 air readings, with a changing sensor network. DEQ’s November 6 report updates the earlier record of ambient air readings in Loudoun and Prince William counties, with seven sensors operating across both counties. Coverage begins in March but varies by site; daily fine-particle averages end November 5. On November 4, sensor 8 moved from Broad Run High School to Discovery Elementary. A new site’s short record is not a continuous history at the old location. The sensors are not regulatory instruments for determining attainment of national air-quality standards, and agreement with regulatory monitors varies by instrument and pollutant. These are air measurements, not a calculation of what data-center generators contributed or evidence of illness. DEQ, November 6, 2026 report, pp. 2–4, 14–17 and 23–29 ↗ Earlier October 30 report ↗
Virginia's newer generator controls are not an emissions reading. DEQ's APG-576 guidance became effective April 9, 2026. Its updated data-center provisions apply to applications received on or after July 1, setting presumptive pollution controls for emergency and non-emergency diesel generators, often called Tier 4-equivalent. Permits remain case by case, with exceptions for some backup-of-backup units, non-server equipment and modifications to existing emergency units. New or replacement units get different treatment. Separate PSD and nonattainment permitting reviews sit outside this guidance. This does not show that every existing generator was upgraded or neighborhood pollution fell. Ask for the site's permit, operating hours and performance tests. DEQ's guidance summary ↗ Effective document and scope, sections A, B and D ↗
October 16 correction: the later final rule also belongs here. Virginia's October 5 Register published a final generator-emissions rule with a November 4 effective date. Its applicability text covers data centers applying for permits on or after July 1, 2026. The rule sets a Tier 4-equivalent emissions ceiling for each generator in covered permits and permits stricter limits. Publication, applicability and effective dates are different. Read this later rule separately from the older guidance and its exceptions; this overview does not decide an individual permit's legal treatment. Neither document measures actual emissions or a local health outcome. Virginia Register, October 5 final rule, 9VAC5-50-610 through -630 ↗
October 12 follow-up: DOE's new PJM order permits last-resort backup dispatch for October 13–16 and excludes critical backup needs. It requires daily reports of operated resources and temporarily changes rolling-average environmental-limit accounting. None of this measures local operation or harm. Original order, pp. 7–8 ↗ Read the current record →
October 13 update: PJM's version 2 resource list, submitted October 12 and posted October 13, adds oil-fired units. It identifies additional resources, not which ones operated or a measured pollution total. Revised Exhibit A, pp. 5 and 11 ↗ Read the updated record →
October 15 correction: PJM's updated account reports demand-response actions on October 13 and 14, not use of large-load backup generation as of that account. Earlier we named only October 13. Dated operator account ↗ Separate the action from the permission →
A quiet baseline is not a health finding. An April 30, 2026 report commissioned by Protect Stafford monitored background sound near three proposed Stafford County data-center sites in two campaigns between January 30 and February 26. Its nighttime minimum-background statistics across six locations were 20–29 dB(A), not all-night averages. About a quarter of recorded time was excluded for weather. The report warns that the 55 dB(A) limit it reviewed could still allow intrusive sound. This is planning evidence, not measured operating noise, a verified violation or proof of illness. Check current project terms and compare before-and-after sound on the same basis. Original report, pp. 5–10 and Table 3 →
JLARC records Brook Haven residents contacting Loudoun about noise in 2021 and an attempted solution completed in November 2023. Residents reported reduced noise after repeated communications. This does not establish a clinical outcome or resolution today. Audit account, p. 77 ↗
What about claims of illness from low frequencies? A narrative review posted October 2, 2026 found no peer-reviewed data-center-specific epidemiological studies in the sources it searched through July 2026. That bounded finding is not proof that no such study exists or that facilities are safe. It proposes better exposure measurements; its possible health pathways are not observed illness.
November 4 addition / study published October 19. A systematic review of 36 studies found environmental pressures and modeled health impacts, but no observed human-health outcomes in the studies it included. Database searches ended July 31, 2026; supplementary Google Scholar searching was August 10. Those are search dates, not new measurements or proof of safety. The authors warn that some facility-level records may have been missed.
WHO identifies sleep disturbance as a risk of excessive environmental noise generally. It does not assign a disease rate to data-center neighbors. For pollution, ATSDR distinguishes exposure from harmful health effects: concentration, duration and frequency matter.
Our test: source → exposure → outcome, with competing explanations checked. A complaint is evidence of a complaint; a model is an estimate. Neither deserves a fake diagnosis—or a fake all-clear. Developers and officials can change siting, operating terms and monitoring. The neighbor cannot move a generator by closing a window.
These are testable formulations, not quotations from a measured sample of posts. We have not counted how often they circulate.
Too absolute. Construction, operations and supporting trades are real. Their duration and size differ. State audit ↗
Wrong clock. The roughly 1,500-worker example is a peak construction figure; the reported operating example is roughly 50 full-time workers. State audit ↗
Not in Loudoun. The county reports actual fiscal 2026 receipts. A new locality still needs its own forecast, incentive terms and later collections. County figures ↗
Also wrong. The Virginia audit documented both planning pressures and site-to-site variation. Measure the project; don't wave away its neighbors. State audit ↗
A community can gain tax revenue, school resources, well-paid work and useful infrastructure. It can also inherit expensive power needs, water demands or a building where homes should have had quiet. Loudoun shows that benefits can be substantial. It does not absolve the next developer from showing the terms. Ask what was promised, what was collected, who got the work, who pays for the grid, and what can be measured after opening. That is not a conspiracy theory. It is local government doing its homework.
A huge construction total can sound like permanent employment; a small statewide water share can sound like no local pressure. Both require the project’s period, geography and denominator.
Actual tax receipts net of incentives, approved tariffs, metered loads, water agreements and operating employment would change a project-specific ledger. Compare them with a credible alternative use of the site.
Source roles matter: the county and school division describe their own budgets; JLARC audits statewide evidence; EPA estimates national irrigation; Berkeley Lab estimates national power use; EIA models a scenario. Their links are not interchangeable corroboration. This is a bounded fact file, not a verdict on a specific proposed facility.